Outline of intended schedule to deliver.

Broad Overview

Requires

25th February
General Query work
GenericQueryView, ListingsView and ChannelView displaying properly
Basic DetailsView
Very basic Config
Query work in place, Config work behind schedule. ListingsView complete, ChannelView caught up slightly.
4th March
Continue investigating optimising recording performance.
Parsing of XML listings from arbitrary URL into attributed files.
Annotating listings entries with requests to record, etc.
Full DetailsView and working (local) searching
Local searching not in place. Parsing of XML done. ChannelView complete, waiting on a richer SingleProgrammeView to be more useful. Things progressing appropriately to catch up this weekend (10th).
11th March
Focus on improving recording app, querying listings files and quality thresholds.
Work on invocation of Player app (relatively simple)
Server-side work on collating behavioural information. Put calls to Collaboration Server in videdot App.
18th March
Clean up remaining interface. Presentable interface to extended Config.
Simple Network Searching

Some lee-way is left towards the end of term, to account for delays and difficulties.

This leaves us with a reasonable implementation by the end of term, which broadly covers the intended aims of the project. The install-time configuration is left to be implemented next term. Further enhancements next term would include subtitling, set-top-box support and enhanced collaboration features.